Ministry says data centres will not hurt household power supply
The Ministry of Energy Transition and Water Transformation said national electricity supply capacity is currently assured and that measures are in place to stop data centres affecting domestic and existing industrial users, Bernama reported via FMT. It gave the answer in a written parliamentary reply to Kuala Kangsar MP Iskandar Dzulkarnain Abdul Khalid.
Key points
- An Ultra High Voltage tariff has applied since 1 July 2025 to data centres supplied above 50kV, so operators bear their own infrastructure costs.
- A higher connected load charge is meant to prevent unused, stranded capacity.
- Data centres must use at least 30 per cent renewable energy.
- Data centre power quotas are approved through the National Energy Council and finalised by the Data Centre Task Force.
Why it matters for Malaysia
Power is the main limit on data centre growth, and public concern about household bills is rising. The reply sets out the rules operators face on tariffs, load and renewables.
Questions answered
- How does the government protect other electricity users from data centre demand?
- The ministry said it introduced an Ultra High Voltage tariff from 1 July 2025 and a higher connected load charge, requires at least 30 per cent renewable energy, and encourages self-generation and backup power during peak periods.
- Who decides how much power data centres can get?
- The ministry said demand projections approved by the Electricity Supply Planning and Implementation and Tariff Committee are converted into data centre quotas through the National Energy Council. The Data Centre Task Force, serviced by MITI and the Ministry of Digital, then finalises them.